Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 06:53:12.593559
Works ongoing
12,627
Sanctioned (pure scheme)
₹120.30 Cr
Expenditure since inception
₹5.59 Cr
Balance cost (unspent)
₹114.72 Cr
Wage ₹69.72 Cr · Material ₹44.99 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,149 works
₹34.49 Cr sanctioned
₹44.40 L spent (1%)
02
Rural Housing
9,334 works
₹25.20 Cr sanctioned
₹2.70 Cr spent (11%)
03
Construction of Well
845 works
₹21.10 Cr sanctioned
₹14.91 L spent (1%)
04
Construction of Check Dam/Stop Dam
177 works
₹8.13 Cr sanctioned
₹35.00 L spent (4%)
05
Construction of Trench
151 works
₹6.17 Cr sanctioned
₹73.05 L spent (12%)
06
Cattle Shed
242 works
₹5.66 Cr sanctioned
₹84.18 L spent (15%)
07
Farm Pond
117 works
₹2.77 Cr sanctioned
₹1.64 L spent (1%)
08
Construction of Tank
55 works
₹2.43 Cr sanctioned
₹17.31 L spent (7%)
09
Construction of Percolation Tank
20 works
₹1.76 Cr sanctioned
₹6.31 L spent (4%)
10
Construction of Road and Culvert
14 works
₹1.54 Cr sanctioned
₹0 spent (0%)