Monitor — Ongoing Works
Rollup last refreshed: 2026-10-04 06:52:14.898992
Works ongoing
6,089
Sanctioned (pure scheme)
₹201.88 Cr
Expenditure since inception
₹8.52 Cr
Balance cost (unspent)
₹193.36 Cr
Wage ₹104.38 Cr · Material ₹88.98 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
899 works
₹55.30 Cr sanctioned
₹5.17 Cr spent (9%)
02
Plantation
1,402 works
₹44.05 Cr sanctioned
₹93.65 L spent (2%)
03
Construction of Check Dam/Stop Dam
532 works
₹21.80 Cr sanctioned
₹1.12 Cr spent (5%)
04
Construction of Tank
150 works
₹18.06 Cr sanctioned
₹36.20 L spent (2%)
05
Construction of Well
294 works
₹7.72 Cr sanctioned
₹26,864 spent (0%)
06
Constr of Compound wall
57 works
₹6.77 Cr sanctioned
₹0 spent (0%)
07
Rural Housing
1,843 works
₹5.24 Cr sanctioned
₹57.70 L spent (11%)
08
Construction of Road and Culvert
26 works
₹4.45 Cr sanctioned
₹60,262 spent (0%)
09
Constr of Cement Concrete Roads
46 works
₹4.43 Cr sanctioned
₹0 spent (0%)
10
Well Recharge
88 works
₹3.57 Cr sanctioned
₹1.28 L spent (0%)