Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
7
Sanctioned (pure scheme)
₹36.84 L
Expenditure since inception
₹19.23 L
Balance cost (unspent)
₹17.60 L
Wage ₹6.48 L · Material ₹11.12 L
Expenditure trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Compound wall
1 works
₹15.00 L sanctioned
₹14.19 L spent (95%)
02
Construction of Tank
1 works
₹11.74 L sanctioned
₹1.68 L spent (14%)
03
Construction of Spur
1 works
₹4.79 L sanctioned
₹47,082 spent (10%)
04
Construction of Check Dam/Stop Dam
1 works
₹3.33 L sanctioned
₹1.92 L spent (58%)
05
Constr of Cement Concrete Roads
2 works
₹1.42 L sanctioned
₹79,358 spent (56%)
06
Plantation
1 works
₹56,046 sanctioned
₹18,725 spent (33%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)