Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
7,620
Sanctioned (pure scheme)
₹246.69 Cr
Expenditure since inception
₹130.01 Cr
Balance cost (unspent)
₹116.68 Cr
Wage ₹72.76 Cr · Material ₹43.92 Cr
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
301 works
₹75.56 Cr sanctioned
₹49.42 Cr spent (65%)
02
Plantation
3,639 works
₹65.45 Cr sanctioned
₹18.15 Cr spent (28%)
03
Construction of Check Dam/Stop Dam
242 works
₹38.90 Cr sanctioned
₹29.20 Cr spent (75%)
04
Construction of Well
1,006 works
₹30.28 Cr sanctioned
₹14.17 Cr spent (47%)
05
Construction of Percolation Tank
64 works
₹7.24 Cr sanctioned
₹4.54 Cr spent (63%)
06
Constr of Cement Concrete Roads
146 works
₹7.19 Cr sanctioned
₹5.57 Cr spent (78%)
07
Rural Housing
1,548 works
₹4.18 Cr sanctioned
₹1.85 Cr spent (44%)
08
Farm Pond
161 works
₹4.16 Cr sanctioned
₹1.11 Cr spent (27%)
09
Construction of Road and Culvert
19 works
₹2.38 Cr sanctioned
₹1.72 Cr spent (72%)
10
Well Recharge
106 works
₹2.25 Cr sanctioned
₹61.92 L spent (28%)