Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
3,893
Sanctioned (pure scheme)
₹78.20 Cr
Expenditure since inception
₹30.02 Cr
Balance cost (unspent)
₹48.18 Cr
Wage ₹24.23 Cr · Material ₹23.95 Cr
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
629 works
₹17.30 Cr sanctioned
₹4.74 Cr spent (27%)
02
Construction of Tank
62 works
₹8.11 Cr sanctioned
₹4.68 Cr spent (58%)
03
Construction of Well
154 works
₹4.89 Cr sanctioned
₹2.13 Cr spent (43%)
04
Repair & maint of Pond/ Tank
67 works
₹4.81 Cr sanctioned
₹2.50 Cr spent (52%)
05
Constr of Cement Concrete Roads
116 works
₹4.51 Cr sanctioned
₹83.26 L spent (18%)
06
Rural Housing
1,815 works
₹4.27 Cr sanctioned
₹2.53 Cr spent (59%)
07
Construction of Trench
48 works
₹4.11 Cr sanctioned
₹1.19 Cr spent (29%)
08
Construction of Bund
89 works
₹3.90 Cr sanctioned
₹1.55 Cr spent (40%)
09
Construction of Check Dam/Stop Dam
28 works
₹3.21 Cr sanctioned
₹1.87 Cr spent (58%)
10
Farm Pond
192 works
₹2.79 Cr sanctioned
₹92.66 L spent (33%)