Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
24
Sanctioned (pure scheme)
₹2.44 Cr
Expenditure since inception
₹1.46 Cr
Balance cost (unspent)
₹98.26 L
Wage ₹58.74 L · Material ₹39.51 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
8 works
₹1.10 Cr sanctioned
₹31.12 L spent (28%)
02
Plantation
9 works
₹76.55 L sanctioned
₹70.57 L spent (92%)
03
Constr of Cement Concrete Roads
2 works
₹25.01 L sanctioned
₹20.75 L spent (83%)
04
Works for Flood Control and Protection
2 works
₹20.02 L sanctioned
₹17.62 L spent (88%)
05
Farm Pond
2 works
₹8.96 L sanctioned
₹3.25 L spent (36%)
06
Construction of Trench
1 works
₹3.48 L sanctioned
₹2.75 L spent (79%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)