Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
20
Sanctioned (pure scheme)
₹32.75 L
Expenditure since inception
₹9.90 L
Balance cost (unspent)
₹22.84 L
Wage ₹13.36 L · Material ₹9.48 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1 works
₹11.09 L sanctioned
₹5.39 L spent (49%)
02
Construction of Road and Culvert
1 works
₹8.91 L sanctioned
₹18,240 spent (2%)
03
Construction of Well
1 works
₹3.41 L sanctioned
₹2.37 L spent (69%)
04
Rural Housing
14 works
₹3.29 L sanctioned
₹1.79 L spent (54%)
05
Construction of Bund
1 works
₹3.10 L sanctioned
₹15,960 spent (5%)
06
Constr of Aganwadi
1 works
₹2.69 L sanctioned
₹884 spent (0%)
07
Well Recharge
1 works
₹25,899 sanctioned
₹261 spent (1%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)