Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
70
Sanctioned (pure scheme)
₹1.13 Cr
Expenditure since inception
₹14.48 L
Balance cost (unspent)
₹98.84 L
Wage ₹57.54 L · Material ₹41.31 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹79.31 L sanctioned
₹94,482 spent (1%)
02
Rural Housing
61 works
₹14.33 L sanctioned
₹7.97 L spent (56%)
03
Construction of Well
3 works
₹8.43 L sanctioned
₹1.01 L spent (12%)
04
Construction of Percolation Tank
1 works
₹5.37 L sanctioned
₹42,039 spent (8%)
05
Construction of Trench
1 works
₹5.37 L sanctioned
₹4.13 L spent (77%)
06
Well Recharge
1 works
₹25,899 sanctioned
₹0 spent (0%)
07
Construction of Recharge Pits
1 works
₹25,177 sanctioned
₹261 spent (1%)
08
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)