Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
8
Sanctioned (pure scheme)
₹5.22 L
Expenditure since inception
₹1.77 L
Balance cost (unspent)
₹3.45 L
Wage ₹3.15 L · Material ₹30,000
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Aganwadi
2 works
₹3.60 L sanctioned
₹89,778 spent (25%)
02
Rural Housing
6 works
₹1.62 L sanctioned
₹87,696 spent (54%)
03
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
04
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)