Monitor — Ongoing Works
Rollup last refreshed: 2026-10-12 07:04:13.185207
Works ongoing
32
Sanctioned (pure scheme)
₹22.24 L
Expenditure since inception
₹12.71 L
Balance cost (unspent)
₹9.53 L
Wage ₹5.88 L · Material ₹3.65 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
6 works
₹8.95 L sanctioned
₹3.28 L spent (37%)
02
Rural Housing
18 works
₹4.86 L sanctioned
₹3.37 L spent (69%)
03
Construction of Crematorium
1 works
₹2.68 L sanctioned
₹2.39 L spent (89%)
04
Constr of Cement Concrete Roads
3 works
₹2.07 L sanctioned
₹96,300 spent (47%)
05
Construction of Well
1 works
₹2.00 L sanctioned
₹1.28 L spent (64%)
06
Construction of NADEP/Vermi Compost Pit
2 works
₹1.30 L sanctioned
₹1.17 L spent (91%)
07
Solid and Liquid Waste Management
1 works
₹39,000 sanctioned
₹24,600 spent (63%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)