Monitor — Ongoing Works
Rollup last refreshed: 2026-10-11 07:05:01.394862
Works ongoing
11
Sanctioned (pure scheme)
₹32.57 L
Expenditure since inception
₹9.24 L
Balance cost (unspent)
₹23.33 L
Wage ₹13.38 L · Material ₹9.95 L
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
- KHARGONE — BHAGVANPURA-1,410
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Grass Land Development
2 works
₹16.25 L sanctioned
₹4.97 L spent (31%)
02
Constr of GP Bhawan
1 works
₹7.57 L sanctioned
₹1.79 L spent (24%)
03
Plantation
3 works
₹4.20 L sanctioned
₹1.24 L spent (29%)
04
Construction of Crematorium
1 works
₹1.80 L sanctioned
₹37,878 spent (21%)
05
Constr of Compound wall
1 works
₹1.20 L sanctioned
₹51,568 spent (43%)
06
Construction of Check Dam/Stop Dam
1 works
₹1.00 L sanctioned
₹380 spent (0%)
07
Rural Housing
2 works
₹54,000 sanctioned
₹34,578 spent (64%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)