Monitor — Ongoing Works
Rollup last refreshed: 2026-09-26 07:03:36.929547
Works ongoing
9
Sanctioned (pure scheme)
₹32.76 L
Expenditure since inception
₹14.63 L
Balance cost (unspent)
₹18.13 L
Wage ₹8.10 L · Material ₹10.02 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
5 works
₹16.03 L sanctioned
₹7.92 L spent (49%)
02
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹8.21 L sanctioned
₹1.43 L spent (17%)
03
Plantation
2 works
₹5.69 L sanctioned
₹2.75 L spent (48%)
04
Construction of NADEP/Vermi Compost Pit
1 works
₹2.82 L sanctioned
₹2.54 L spent (90%)
05
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)