Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
3
Sanctioned (pure scheme)
₹2.37 L
Expenditure since inception
₹1.38 L
Balance cost (unspent)
₹99,605
Wage ₹58,506 · Material ₹41,099
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1 works
₹1.80 L sanctioned
₹1.32 L spent (73%)
02
Rural Housing
2 works
₹57,000 sanctioned
₹5,790 spent (10%)
03
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
04
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Fish Drying Infrastructure
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)