Monitor — Ongoing Works
Rollup last refreshed: 2026-09-14 07:02:51.614626
Works ongoing
19
Sanctioned (pure scheme)
₹32.58 L
Expenditure since inception
₹5.44 L
Balance cost (unspent)
₹27.14 L
Wage ₹16.17 L · Material ₹10.97 L
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
10 works
₹21.78 L sanctioned
₹5.07 L spent (23%)
02
Construction of Tank
1 works
₹5.71 L sanctioned
₹19,000 spent (3%)
03
Construction of Check Dam/Stop Dam
3 works
₹2.27 L sanctioned
₹16,970 spent (7%)
04
Construction of Bund
3 works
₹1.93 L sanctioned
₹570 spent (0%)
05
Boulder Check/Gully Plug
1 works
₹61,441 sanctioned
₹190 spent (0%)
06
Rural Housing
1 works
₹28,500 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)