Monitor — Ongoing Works
Rollup last refreshed: 2026-10-15 10:09:22.008812
Works ongoing
28
Sanctioned (pure scheme)
₹3.40 Cr
Expenditure since inception
₹1.55 L
Balance cost (unspent)
₹3.39 Cr
Wage ₹2.47 Cr · Material ₹91.71 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
22 works
₹3.13 Cr sanctioned
₹31,320 spent (0%)
02
Construction of Check Dam/Stop Dam
1 works
₹13.45 L sanctioned
₹1.24 L spent (9%)
03
Plantation
5 works
₹13.16 L sanctioned
₹0 spent (0%)
04
Repair & maint of Pond/ Tank
0 works
₹0 sanctioned
₹0 spent (0%)
05
Works for Flood Control and Protection
0 works
₹0 sanctioned
₹0 spent (0%)