MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
939
Sanctioned (pure scheme)
₹91.45 Cr
Expenditure since inception
₹41.55 Cr
Balance cost (unspent)
₹49.91 Cr
Wage ₹30.82 Cr · Material ₹19.09 Cr
Expenditure trend
₹56.93 Cr
This Week
₹182.70 Cr
Last Week
▼ 68.8% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
  • MORENA — JOURA−₹1.63 Cr
Mandays trend
2,63,410
This Week
21,46,699
Last Week
▼ 87.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,502

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
348 works
₹50.08 Cr sanctioned
₹23.24 Cr spent (46%)
02
Construction of Check Dam/Stop Dam
71 works
₹10.20 Cr sanctioned
₹4.54 Cr spent (45%)
03
Plantation
136 works
₹6.90 Cr sanctioned
₹2.30 Cr spent (33%)
04
Construction of Bund
31 works
₹3.83 Cr sanctioned
₹1.96 Cr spent (51%)
05
Construction of Road and Culvert
19 works
₹3.78 Cr sanctioned
₹1.42 Cr spent (38%)
06
Works for Flood Control and Protection
39 works
₹3.39 Cr sanctioned
₹1.80 Cr spent (53%)
07
Farm Pond
81 works
₹3.21 Cr sanctioned
₹1.10 Cr spent (34%)
08
Constr of Cement Concrete Roads
67 works
₹1.25 Cr sanctioned
₹87.18 L spent (70%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
12 works
₹1.04 Cr sanctioned
₹47.12 L spent (45%)
10
Terracing
6 works
₹84.21 L sanctioned
₹59.55 L spent (71%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Construction of Tank 348 50.08 23.24 26.84
46%
2 Plantation 136 6.90 2.30 4.60
33%
3 Farm Pond 81 3.21 1.10 2.11
34%
4 Construction of Check Dam/Stop Dam 71 10.20 4.54 5.66
45%
5 Constr of Cement Concrete Roads 67 1.25 0.87 0.38
70%
6 Works for Flood Control and Protection 39 3.39 1.80 1.59
53%
7 Construction of Bund 31 3.83 1.96 1.87
51%
8 Rural Housing 22 0.05 0.02 0.03
45%
9 Construction of Road and Culvert 19 3.78 1.42 2.36
38%
10 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 12 1.04 0.47 0.57
45%
11 Well Recharge 12 0.04 0.01 0.04
15%
12 Construction of Recharge Pits 9 0.15 0.09 0.06
59%
13 Construction of Crematorium 8 0.25 0.04 0.21
16%
14 Construction of Trench 8 0.60 0.46 0.15
76%
15 Constr of Aganwadi 8 0.34 0.16 0.17
49%
16 Boulder Check/Gully Plug 7 0.38 0.22 0.16
58%
17 Constr of GP Bhawan 7 0.65 0.31 0.34
47%
18 Land Development 6 0.57 0.17 0.40
30%
19 Terracing 6 0.84 0.60 0.25
71%
20 Cattle Shed 6 0.07 0.00 0.07
1%
21 Constr of Gabion 5 0.73 0.36 0.38
49%
22 Constr of Food Grain storage 5 0.48 0.39 0.08
83%
23 Construction of Well 3 0.04 0.00 0.03
9%
24 Construction of Embankment 3 0.17 0.13 0.04
77%
25 Grass Land Development 3 0.29 0.13 0.16
45%
26 Nursery Development 3 0.55 0.04 0.51
8%
27 Construction of Spur 2 0.28 0.27 0.01
96%
28 Construction of Percolation Tank 2 0.49 0.26 0.23
54%
29 Repair & Maint of Check Dam/Stop Dam 2 0.30 0.04 0.26
13%
30 Construction of NADEP/Vermi Compost Pit 1 0.13 0.11 0.02
81%
31 Repair & Maint of Canal 1 0.04 0.00 0.04
2%
32 Construction of Toilets 1 0.01 0.01 0.00
87%
33 Repair & maint of Pond/ Tank 1 0.01 0.00 0.01
2%
34 Underground Dyke for Ground Water Recharge 1 0.15 0.00 0.14
1%
35 Community Sanitary Complex 1 0.01 0.00 0.00
62%
36 Roof Water Harvesting on gov/panchayat bldg 1 0.00 0.00 0.00
0%
37 Solid and Liquid Waste Management 1 0.14 0.01 0.13
6%
Total 939 91.45 41.55 49.91
All 37 rows (zero-value rows hidden) ⇩ Export to Excel