MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
1,204
Sanctioned (pure scheme)
₹108.43 Cr
Expenditure since inception
₹66.52 Cr
Balance cost (unspent)
₹41.90 Cr
Wage ₹26.61 Cr · Material ₹15.29 Cr
Expenditure trend
₹56.93 Cr
This Week
₹182.70 Cr
Last Week
▼ 68.8% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
  • MORENA — JOURA−₹1.63 Cr
Mandays trend
2,63,410
This Week
21,46,699
Last Week
▼ 87.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,502

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
279 works
₹42.30 Cr sanctioned
₹27.82 Cr spent (66%)
02
Construction of Bund
229 works
₹24.88 Cr sanctioned
₹15.80 Cr spent (64%)
03
Works for Flood Control and Protection
89 works
₹11.36 Cr sanctioned
₹6.31 Cr spent (56%)
04
Construction of Check Dam/Stop Dam
59 works
₹8.29 Cr sanctioned
₹5.91 Cr spent (71%)
05
Plantation
152 works
₹5.79 Cr sanctioned
₹1.52 Cr spent (26%)
06
Construction of Road and Culvert
25 works
₹5.41 Cr sanctioned
₹3.73 Cr spent (69%)
07
Construction of Percolation Tank
10 works
₹1.48 Cr sanctioned
₹86.54 L spent (59%)
08
Farm Pond
85 works
₹1.47 Cr sanctioned
₹74.04 L spent (50%)
09
Construction of Trench
6 works
₹87.62 L sanctioned
₹60.10 L spent (69%)
10
Grass Land Development
11 works
₹86.41 L sanctioned
₹26.23 L spent (30%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Construction of Tank 279 42.30 27.82 14.48
66%
2 Construction of Bund 229 24.88 15.80 9.07
64%
3 Plantation 152 5.79 1.52 4.27
26%
4 Works for Flood Control and Protection 89 11.36 6.31 5.05
56%
5 Farm Pond 85 1.47 0.74 0.73
50%
6 Construction of Check Dam/Stop Dam 59 8.29 5.91 2.38
71%
7 Well Recharge 51 0.13 0.04 0.09
34%
8 Rural Housing 45 0.11 0.08 0.02
77%
9 Construction of Recharge Pits 42 0.10 0.02 0.08
22%
10 Constr of Cement Concrete Roads 26 0.19 0.10 0.09
55%
11 Construction of Road and Culvert 25 5.41 3.73 1.68
69%
12 Construction of Crematorium 22 0.62 0.38 0.23
62%
13 Construction of NADEP/Vermi Compost Pit 20 0.32 0.12 0.20
38%
14 Community Sanitary Complex 11 0.36 0.04 0.32
12%
15 Grass Land Development 11 0.86 0.26 0.60
30%
16 Construction of Percolation Tank 10 1.48 0.87 0.61
59%
17 Boulder Check/Gully Plug 8 0.86 0.58 0.29
67%
18 Constr of Aganwadi 7 0.27 0.08 0.19
29%
19 Construction of Trench 6 0.88 0.60 0.28
69%
20 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 4 0.59 0.38 0.21
65%
21 Land Development 4 0.35 0.16 0.19
47%
22 Constr of GP Bhawan 3 0.18 0.13 0.05
73%
23 Constr of Compound wall 3 0.08 0.03 0.04
43%
24 Construction of Embankment 2 0.24 0.18 0.06
75%
25 Repair & maint of Pond/ Tank 2 0.15 0.03 0.12
22%
26 Repaire and Maint of NADEP/Vermi Compost Pit 2 0.06 0.01 0.06
9%
27 Repair & Maint of Bund 1 0.12 0.04 0.08
30%
28 Constr of Gabion 1 0.15 0.13 0.02
88%
29 Construction of Play field 1 0.04 0.03 0.01
69%
30 Construction of Spur 1 0.15 0.15 0.00
97%
31 Nursery Development 1 0.50 0.13 0.38
26%
32 Repair & Maint of Community infrastructure 1 0.03 0.03 0.00
89%
33 Repair & maint of Water Harvesting Structures 1 0.11 0.08 0.03
76%
Total 1,204 108.43 66.52 41.90
All 33 rows (zero-value rows hidden) ⇩ Export to Excel