Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Works ongoing
7
Sanctioned (pure scheme)
₹90.78 L
Expenditure since inception
₹83.16 L
Balance cost (unspent)
₹7.62 L
Wage ₹5.28 L · Material ₹2.34 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹30.27 L sanctioned
₹27.69 L spent (91%)
02
Construction of Bund
2 works
₹27.67 L sanctioned
₹26.32 L spent (95%)
03
Construction of Check Dam/Stop Dam
1 works
₹14.99 L sanctioned
₹13.19 L spent (88%)
04
Constr of Gabion
1 works
₹14.58 L sanctioned
₹13.06 L spent (90%)
05
Solid and Liquid Waste Management
1 works
₹3.27 L sanctioned
₹2.91 L spent (89%)
06
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)
10
Culvert
0 works
₹0 sanctioned
₹0 spent (0%)