Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
23
Sanctioned (pure scheme)
₹3.18 Cr
Expenditure since inception
₹1.46 Cr
Balance cost (unspent)
₹1.72 Cr
Wage ₹1.12 Cr · Material ₹59.59 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
- KHANDWA — PANDHANA−₹93.68 L
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
11 works
₹1.57 Cr sanctioned
₹61.35 L spent (39%)
02
Construction of Check Dam/Stop Dam
5 works
₹74.08 L sanctioned
₹61.15 L spent (83%)
03
Construction of Percolation Tank
1 works
₹38.43 L sanctioned
₹11.16 L spent (29%)
04
Construction of Trench
1 works
₹23.54 L sanctioned
₹2,112 spent (0%)
05
Repair & Maint of Check Dam/Stop Dam
1 works
₹14.85 L sanctioned
₹10.22 L spent (69%)
06
Plantation
4 works
₹9.98 L sanctioned
₹2.31 L spent (23%)
07
Construction of Embankment
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Spur
0 works
₹0 sanctioned
₹0 spent (0%)