Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
47
Sanctioned (pure scheme)
₹5.37 Cr
Expenditure since inception
₹3.32 Cr
Balance cost (unspent)
₹2.05 Cr
Wage ₹1.53 Cr · Material ₹51.86 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
- KHANDWA — PANDHANA−₹93.68 L
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
11 works
₹2.02 Cr sanctioned
₹1.47 Cr spent (73%)
02
Construction of Bund
6 works
₹90.04 L sanctioned
₹53.49 L spent (59%)
03
Construction of Trench
6 works
₹89.14 L sanctioned
₹75.20 L spent (84%)
04
Nursery Development
1 works
₹58.19 L sanctioned
₹1.42 L spent (2%)
05
Land Development
3 works
₹57.23 L sanctioned
₹30.22 L spent (53%)
06
Terracing
1 works
₹14.96 L sanctioned
₹9.97 L spent (67%)
07
Construction of Embankment
1 works
₹14.79 L sanctioned
₹10.57 L spent (71%)
08
Farm Pond
3 works
₹7.46 L sanctioned
₹2.64 L spent (35%)
09
Rural Housing
14 works
₹3.11 L sanctioned
₹1.03 L spent (33%)
10
Community Sanitary Complex
1 works
₹43,000 sanctioned
₹32,424 spent (75%)