Monitor — Ongoing Works
Rollup last refreshed: 2026-10-20 07:05:33.239245
Works ongoing
22
Sanctioned (pure scheme)
₹2.92 Cr
Expenditure since inception
₹2.11 Cr
Balance cost (unspent)
₹81.37 L
Wage ₹60.88 L · Material ₹20.49 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
- CHHATARPUR — CHHATARPUR-28
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
13 works
₹1.94 Cr sanctioned
₹1.48 Cr spent (76%)
02
Plantation
4 works
₹36.52 L sanctioned
₹16.82 L spent (46%)
03
Repair & maint of Road
1 works
₹24.90 L sanctioned
₹21.10 L spent (85%)
04
Construction of Check Dam/Stop Dam
1 works
₹14.97 L sanctioned
₹9.79 L spent (65%)
05
Works for Flood Control and Protection
1 works
₹14.49 L sanctioned
₹11.53 L spent (80%)
06
Nursery Development
1 works
₹4.54 L sanctioned
₹2.65 L spent (58%)
07
Construction of Trench
1 works
₹3.31 L sanctioned
₹1.57 L spent (47%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)