Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
22
Sanctioned (pure scheme)
₹3.34 Cr
Expenditure since inception
₹2.06 Cr
Balance cost (unspent)
₹1.28 Cr
Wage ₹86.04 L · Material ₹41.94 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
- KHANDWA — PANDHANA−₹93.68 L
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
10 works
₹1.49 Cr sanctioned
₹99.59 L spent (67%)
02
Construction of Bund
8 works
₹1.27 Cr sanctioned
₹59.11 L spent (46%)
03
Works for Flood Control and Protection
2 works
₹29.65 L sanctioned
₹25.39 L spent (86%)
04
Construction of Road and Culvert
1 works
₹24.88 L sanctioned
₹21.85 L spent (88%)
05
Plantation
1 works
₹3.10 L sanctioned
₹14,580 spent (5%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Boulder Check/Gully Plug
0 works
₹0 sanctioned
₹0 spent (0%)