Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
47
Sanctioned (pure scheme)
₹7.00 Cr
Expenditure since inception
₹3.46 Cr
Balance cost (unspent)
₹3.54 Cr
Wage ₹3.04 Cr · Material ₹49.48 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
29 works
₹4.27 Cr sanctioned
₹1.82 Cr spent (43%)
02
Construction of Check Dam/Stop Dam
10 works
₹1.67 Cr sanctioned
₹80.34 L spent (48%)
03
Construction of Embankment
4 works
₹74.59 L sanctioned
₹61.02 L spent (82%)
04
Land Development
1 works
₹14.97 L sanctioned
₹7.34 L spent (49%)
05
Construction of Tank
1 works
₹12.63 L sanctioned
₹11.77 L spent (93%)
06
Construction of Crematorium
1 works
₹3.31 L sanctioned
₹2.81 L spent (85%)
07
Well Recharge
1 works
₹25,899 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
0 works
₹0 sanctioned
₹0 spent (0%)