Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
5
Sanctioned (pure scheme)
₹47.33 L
Expenditure since inception
₹22.75 L
Balance cost (unspent)
₹24.58 L
Wage ₹17.11 L · Material ₹7.47 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
2 works
₹29.41 L sanctioned
₹22.59 L spent (77%)
02
Works for Flood Control and Protection
1 works
₹14.96 L sanctioned
₹1,326 spent (0%)
03
Farm Pond
2 works
₹2.95 L sanctioned
₹14,616 spent (5%)
04
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)