Works ongoing
10
Sanctioned (pure scheme)
₹97.25 L
Expenditure since inception
₹56.30 L
Balance cost (unspent)
₹40.95 L
Wage ₹30.05 L · Material ₹10.90 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
4 works
₹57.51 L sanctioned
₹38.76 L spent (67%)
02
Construction of Play field
1 works
₹11.20 L sanctioned
₹663 spent (0%)
03
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹10.36 L sanctioned
₹7.30 L spent (70%)
04
Farm Pond
2 works
₹9.02 L sanctioned
₹5.41 L spent (60%)
05
Works for Flood Control and Protection
1 works
₹6.37 L sanctioned
₹4.83 L spent (76%)
06
Plantation
1 works
₹2.80 L sanctioned
₹261 spent (0%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)