MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-08-27 14:06:46.546602
to
Reset filters
Works ongoing
927
Sanctioned (pure scheme)
₹25.46 Cr
Expenditure since inception
₹6.34 Cr
Balance cost (unspent)
₹19.12 Cr
Wage ₹10.12 Cr · Material ₹9.00 Cr
Expenditure trend
−₹1.49 Cr
This Week
−₹1.47 Cr
Last Week
▼ 1.6% vs last week
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹90.28 L
Mandays trend
-94,475
This Week
-1,36,226
Last Week
▲ 30.6%
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
116 works
₹3.82 Cr sanctioned
₹33.00 L spent (9%)
02
Construction of Bund
42 works
₹3.74 Cr sanctioned
₹92.34 L spent (25%)
03
Construction of Check Dam/Stop Dam
25 works
₹2.64 Cr sanctioned
₹56.13 L spent (21%)
04
Construction of Road and Culvert
14 works
₹2.04 Cr sanctioned
₹83.35 L spent (41%)
05
Cattle Shed
29 works
₹2.03 Cr sanctioned
₹1.05 Cr spent (52%)
06
Construction of Tank
12 works
₹1.98 Cr sanctioned
₹22.42 L spent (11%)
07
Farm Pond
55 works
₹1.69 Cr sanctioned
₹28.35 L spent (17%)
08
Rural Housing
417 works
₹97.95 L sanctioned
₹42.97 L spent (44%)
09
Constr of Cement Concrete Roads
62 works
₹93.12 L sanctioned
₹40.22 L spent (43%)
10
Works for Flood Control and Protection
22 works
₹85.94 L sanctioned
₹15.76 L spent (18%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 417 0.98 0.43 0.55
44%
2 Plantation 116 3.82 0.33 3.49
9%
3 Constr of Cement Concrete Roads 62 0.93 0.40 0.53
43%
4 Farm Pond 55 1.69 0.28 1.41
17%
5 Solid and Liquid Waste Management 44 0.09 0.05 0.03
61%
6 Construction of Bund 42 3.74 0.92 2.82
25%
7 Cattle Shed 29 2.03 1.05 0.98
52%
8 Construction of Check Dam/Stop Dam 25 2.64 0.56 2.08
21%
9 Works for Flood Control and Protection 22 0.86 0.16 0.70
18%
10 Construction of Road and Culvert 14 2.04 0.83 1.20
41%
11 Construction of Tank 12 1.98 0.22 1.75
11%
12 Construction of Crematorium 12 0.38 0.12 0.27
30%
13 Constr of GP Bhawan 10 0.73 0.39 0.35
53%
14 Construction of NADEP/Vermi Compost Pit 10 0.02 0.01 0.01
64%
15 Repair & maint of Pond/ Tank 8 0.50 0.05 0.45
10%
16 Constr of Compound wall 7 0.20 0.04 0.16
19%
17 Community Sanitary Complex 5 0.02 0.02 0.01
77%
18 Land Development 5 0.39 0.06 0.34
15%
19 Constr of Kitchen Shed 4 0.17 0.13 0.04
75%
20 Construction of Trench 3 0.32 0.03 0.28
10%
21 Roof Water Harvesting on gov/panchayat bldg 3 0.07 0.01 0.06
19%
22 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 0.05 0.02 0.03
32%
23 Terracing 2 0.15 0.01 0.15
5%
24 Construction of Percolation Tank 2 0.05 0.00 0.05
2%
25 Constr of Aganwadi 2 0.02 0.00 0.02
20%
26 Construction of Spur 2 0.25 0.10 0.15
40%
27 Repair & Maint of Bund 2 0.17 0.04 0.13
23%
28 Construction of Well 2 0.05 0.00 0.05
5%
29 Culvert 1 0.06 0.00 0.06
1%
30 Constr of Food Grain storage 1 0.38 0.00 0.38
0%
31 Construction of Embankment 1 0.25 0.00 0.24
2%
32 Construction of Play field 1 0.03 0.01 0.02
20%
33 Renovation of Canal 1 0.04 0.01 0.03
22%
34 Repair & Maint of Check Dam/Stop Dam 1 0.15 0.04 0.11
30%
35 Repair & maint of Road 1 0.05 0.01 0.04
21%
36 Underground Dyke for Ground Water Recharge 1 0.15 0.01 0.14
5%
Total 927 25.46 6.34 19.12
All 36 rows (zero-value rows hidden) ⇩ Export to Excel