Monitor — Ongoing Works
Rollup last refreshed: 2026-08-29 07:06:35.01532
Works ongoing
7
Sanctioned (pure scheme)
₹78.46 L
Expenditure since inception
₹7.20 L
Balance cost (unspent)
₹71.26 L
Wage ₹45.04 L · Material ₹26.22 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
3 works
₹59.53 L sanctioned
₹3.46 L spent (6%)
02
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹10.00 L sanctioned
₹3.48 L spent (35%)
03
Plantation
1 works
₹5.35 L sanctioned
₹21,156 spent (4%)
04
Construction of Crematorium
1 works
₹3.30 L sanctioned
₹0 spent (0%)
05
Rural Housing
1 works
₹27,000 sanctioned
₹4,698 spent (17%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)