Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
43
Sanctioned (pure scheme)
₹88.88 L
Expenditure since inception
₹33.06 L
Balance cost (unspent)
₹55.82 L
Wage ₹23.80 L · Material ₹32.02 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
2 works
₹23.23 L sanctioned
₹4.41 L spent (19%)
02
Works for Flood Control and Protection
3 works
₹20.66 L sanctioned
₹14.40 L spent (70%)
03
Constr of Cement Concrete Roads
7 works
₹19.77 L sanctioned
₹1.53 L spent (8%)
04
Construction of Embankment
1 works
₹14.97 L sanctioned
₹7.47 L spent (50%)
05
Rural Housing
24 works
₹5.64 L sanctioned
₹4.00 L spent (71%)
06
Construction of Bund
4 works
₹2.71 L sanctioned
₹70,824 spent (26%)
07
Farm Pond
1 works
₹1.48 L sanctioned
₹50,634 spent (34%)
08
Construction of NADEP/Vermi Compost Pit
1 works
₹43,000 sanctioned
₹4,632 spent (11%)
09
Land Development
0 works
₹0 sanctioned
₹0 spent (0%)
10
Other Works
0 works
₹0 sanctioned
₹0 spent (0%)