MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-01 08:37:11.749328
to
Reset filters
Works ongoing
25
Sanctioned (pure scheme)
₹38.42 L
Expenditure since inception
₹6.28 L
Balance cost (unspent)
₹32.14 L
Wage ₹21.53 L · Material ₹10.62 L
Expenditure trend
−₹78.03 L
This Week
−₹1.31 Cr
Last Week
▲ 40.6% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
-33,130
This Week
-34,842
Last Week
▲ 4.9%
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
7 works
₹19.80 L sanctioned
₹5.20 L spent (26%)
02
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹14.27 L sanctioned
₹69,866 spent (5%)
03
Construction of NADEP/Vermi Compost Pit
12 works
₹2.04 L sanctioned
₹30,126 spent (15%)
04
Construction of Check Dam/Stop Dam
1 works
₹1.82 L sanctioned
₹1,215 spent (1%)
05
Construction of Recharge Pits
3 works
₹48,300 sanctioned
₹5,922 spent (12%)
06
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. Panchayat Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 MUSAHARI(P) 25 38.42 6.28 32.14
16%
Total 25 38.42 6.28 32.14
All 1 rows (zero-value rows hidden) ⇩ Export to Excel