Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
15
Sanctioned (pure scheme)
₹33.65 L
Expenditure since inception
₹13.81 L
Balance cost (unspent)
₹19.84 L
Wage ₹12.26 L · Material ₹7.59 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
2 works
₹12.46 L sanctioned
₹6.22 L spent (50%)
02
Constr of GP Bhawan
1 works
₹10.00 L sanctioned
₹5.33 L spent (53%)
03
Plantation
2 works
₹5.33 L sanctioned
₹1,305 spent (0%)
04
Farm Pond
1 works
₹1.95 L sanctioned
₹261 spent (0%)
05
Constr of Aganwadi
1 works
₹1.76 L sanctioned
₹87,876 spent (50%)
06
Rural Housing
7 works
₹1.65 L sanctioned
₹1.30 L spent (79%)
07
Construction of Trench
1 works
₹50,000 sanctioned
₹6,142 spent (12%)
08
Construction of Fish Drying Infrastructure
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)