Monitor — Ongoing Works

Rollup last refreshed: 2026-08-27 14:06:46.546602
to
Reset filters
Works ongoing
2,783
Sanctioned (pure scheme)
₹60.43 Cr
Expenditure since inception
₹25.13 Cr
Balance cost (unspent)
₹35.30 Cr
Wage ₹17.82 Cr · Material ₹17.48 Cr
Expenditure trend
−₹1.49 Cr
This Week
−₹1.47 Cr
Last Week
▼ 1.6% vs last week
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹90.28 L
Mandays trend
-94,475
This Week
-1,36,226
Last Week
▲ 30.6%
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
44 works
₹13.88 Cr sanctioned
₹4.88 Cr spent (35%)
02
Cattle Shed
30 works
₹11.11 Cr sanctioned
₹7.38 Cr spent (66%)
03
Plantation
403 works
₹7.79 Cr sanctioned
₹1.75 Cr spent (22%)
04
Rural Housing
1,581 works
₹3.66 Cr sanctioned
₹2.73 Cr spent (74%)
05
Construction of Tank
34 works
₹2.59 Cr sanctioned
₹42.30 L spent (16%)
06
Construction of Check Dam/Stop Dam
42 works
₹2.54 Cr sanctioned
₹44.01 L spent (17%)
07
Grass Land Development
20 works
₹2.53 Cr sanctioned
₹49.15 L spent (19%)
08
Constr of GP Bhawan
62 works
₹1.89 Cr sanctioned
₹1.11 Cr spent (59%)
09
Constr of Cement Concrete Roads
175 works
₹1.77 Cr sanctioned
₹1.12 Cr spent (64%)
10
Farm Pond
68 works
₹1.71 Cr sanctioned
₹34.24 L spent (20%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,581 3.66 2.73 0.94
74%
2 Plantation 403 7.79 1.75 6.04
22%
3 Constr of Cement Concrete Roads 175 1.77 1.12 0.64
64%
4 Farm Pond 68 1.71 0.34 1.37
20%
5 Constr of GP Bhawan 62 1.89 1.11 0.78
59%
6 Construction of Road and Culvert 44 13.88 4.88 9.00
35%
7 Construction of Check Dam/Stop Dam 42 2.54 0.44 2.10
17%
8 Solid and Liquid Waste Management 42 0.25 0.09 0.16
36%
9 Construction of Well 36 0.87 0.45 0.42
52%
10 Construction of Tank 34 2.59 0.42 2.17
16%
11 Cattle Shed 30 11.11 7.38 3.73
66%
12 Construction of NADEP/Vermi Compost Pit 29 0.24 0.05 0.19
22%
13 Grass Land Development 20 2.53 0.49 2.04
19%
14 Construction of Spur 19 0.97 0.28 0.69
29%
15 Works for Flood Control and Protection 19 0.73 0.28 0.45
38%
16 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 16 0.35 0.14 0.21
39%
17 Construction of Bund 15 0.57 0.26 0.31
46%
18 Constr of Aganwadi 14 0.96 0.76 0.20
79%
19 Land Development 13 0.55 0.13 0.41
25%
20 Construction of Percolation Tank 11 0.35 0.05 0.31
14%
21 Culvert 10 0.67 0.53 0.14
79%
22 Roof Water Harvesting on gov/panchayat bldg 10 0.03 0.00 0.03
12%
23 Construction of Crematorium 10 0.42 0.16 0.26
38%
24 Repair & maint of Pond/ Tank 9 0.50 0.12 0.38
24%
25 Construction of Play field 7 0.15 0.08 0.07
53%
26 Nursery Development 7 0.84 0.09 0.75
11%
27 Constr of Gabion 7 0.29 0.03 0.26
10%
28 Constr of Food Grain storage 6 0.85 0.73 0.12
86%
29 Constr of Compound wall 6 0.04 0.04 0.01
79%
30 Terracing 6 0.09 0.02 0.07
26%
31 Construction of Recharge Pits 5 0.35 0.03 0.32
9%
32 Construction of Trench 4 0.08 0.02 0.06
30%
33 Constr of Kitchen Shed 3 0.01 0.00 0.01
6%
34 Community Sanitary Complex 3 0.07 0.01 0.05
21%
35 Boulder Check/Gully Plug 3 0.21 0.02 0.18
11%
36 Well Recharge 3 0.28 0.04 0.24
15%
37 Repair & Maint of Community infrastructure 2 0.00 0.00 0.00
41%
38 Construction of Other Community Building/Assets 2 0.02 0.00 0.02
18%
39 Repair & Maint of Check Dam/Stop Dam 2 0.05 0.01 0.04
18%
40 Repair & maint of Water Harvesting Structures 2 0.04 0.01 0.02
36%
41 Construction of Toilets 1 0.00 0.00 0.00
97%
42 Construction of building/workshed for SHG 1 0.03 0.00 0.03
8%
43 Repair & maint of Percolation Tank 1 0.07 0.00 0.07
1%
Total 2,783 60.43 25.13 35.30
All 43 rows (zero-value rows hidden) ⇩ Export to Excel