Monitor — Ongoing Works

Rollup last refreshed: 2026-08-27 14:06:46.546602
to
Reset filters
Works ongoing
3,617
Sanctioned (pure scheme)
₹55.92 Cr
Expenditure since inception
₹26.74 Cr
Balance cost (unspent)
₹29.17 Cr
Wage ₹17.49 Cr · Material ₹11.68 Cr
Expenditure trend
−₹1.49 Cr
This Week
−₹1.47 Cr
Last Week
▼ 1.6% vs last week
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹90.28 L
Mandays trend
-94,475
This Week
-1,36,226
Last Week
▲ 30.6%
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-53,337

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
29 works
₹11.09 Cr sanctioned
₹7.05 Cr spent (64%)
02
Construction of Tank
79 works
₹10.34 Cr sanctioned
₹3.12 Cr spent (30%)
03
Plantation
249 works
₹7.28 Cr sanctioned
₹1.76 Cr spent (24%)
04
Rural Housing
2,917 works
₹6.79 Cr sanctioned
₹3.98 Cr spent (59%)
05
Construction of Well
82 works
₹4.25 Cr sanctioned
₹2.24 Cr spent (53%)
06
Construction of Check Dam/Stop Dam
14 works
₹4.23 Cr sanctioned
₹2.69 Cr spent (64%)
07
Land Development
16 works
₹2.06 Cr sanctioned
₹1.56 Cr spent (75%)
08
Construction of Bund
26 works
₹1.27 Cr sanctioned
₹30.94 L spent (24%)
09
Farm Pond
57 works
₹1.15 Cr sanctioned
₹14.04 L spent (12%)
10
Construction of Percolation Tank
11 works
₹1.05 Cr sanctioned
₹57.52 L spent (55%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 2,917 6.79 3.98 2.81
59%
2 Plantation 249 7.28 1.76 5.52
24%
3 Construction of Well 82 4.25 2.24 2.01
53%
4 Construction of Tank 79 10.34 3.12 7.22
30%
5 Farm Pond 57 1.15 0.14 1.01
12%
6 Well Recharge 37 0.49 0.18 0.31
36%
7 Construction of Road and Culvert 29 11.09 7.05 4.04
64%
8 Construction of Bund 26 1.27 0.31 0.96
25%
9 Constr of Cement Concrete Roads 22 0.45 0.25 0.19
57%
10 Land Development 16 2.06 1.56 0.51
76%
11 Construction of Check Dam/Stop Dam 14 4.23 2.69 1.54
64%
12 Constr of GP Bhawan 14 0.68 0.24 0.44
35%
13 Construction of Percolation Tank 11 1.05 0.58 0.47
55%
14 Culvert 10 0.77 0.55 0.22
72%
15 Repair & maint of Pond/ Tank 6 0.34 0.08 0.25
25%
16 Community Sanitary Complex 6 0.06 0.03 0.04
41%
17 Construction of Trench 6 0.67 0.16 0.51
24%
18 Works for Flood Control and Protection 5 0.67 0.58 0.09
87%
19 Construction of Recharge Pits 3 0.02 0.00 0.01
26%
20 Solid and Liquid Waste Management 3 0.04 0.00 0.03
7%
21 Construction of Crematorium 3 0.11 0.08 0.03
71%
22 Constr of Compound wall 3 0.27 0.21 0.06
77%
23 Construction of NADEP/Vermi Compost Pit 3 0.06 0.00 0.06
1%
24 Nursery Development 2 0.06 0.01 0.04
26%
25 Construction of Play field 2 0.07 0.00 0.07
5%
26 Cattle Shed 2 0.76 0.52 0.23
69%
27 Roof Water Harvesting on gov/panchayat bldg 2 0.07 0.00 0.07
7%
28 Repair & maint of Road 1 0.25 0.14 0.11
56%
29 Repair & maint of Gully Plugs 1 0.08 0.03 0.05
40%
30 Repair & Maint of Check Dam/Stop Dam 1 0.10 0.05 0.05
54%
31 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.06 0.00 0.06
3%
32 Grass Land Development 1 0.14 0.04 0.10
30%
33 Boulder Check/Gully Plug 1 0.15 0.13 0.02
87%
34 Construction of building/workshed for SHG 1 0.03 0.00 0.03
9%
35 Constr of Aganwadi 1 0.02 0.00 0.02
8%
Total 3,617 55.92 26.74 29.17
All 35 rows (zero-value rows hidden) ⇩ Export to Excel