Monitor — Ongoing Works
Rollup last refreshed: 2026-08-30 06:52:37.55722
Works ongoing
34
Sanctioned (pure scheme)
₹1.16 Cr
Expenditure since inception
₹75,000
Balance cost (unspent)
₹1.15 Cr
Wage ₹66.70 L · Material ₹48.28 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Embankment
10 works
₹50.82 L sanctioned
₹0 spent (0%)
02
Constr of Cement Concrete Roads
2 works
₹29.35 L sanctioned
₹0 spent (0%)
03
Construction of Trench
1 works
₹11.99 L sanctioned
₹0 spent (0%)
04
Construction of Bund
2 works
₹6.55 L sanctioned
₹0 spent (0%)
05
Works for Flood Control and Protection
1 works
₹6.01 L sanctioned
₹0 spent (0%)
06
Plantation
4 works
₹3.90 L sanctioned
₹0 spent (0%)
07
Construction of Tank
1 works
₹3.33 L sanctioned
₹0 spent (0%)
08
Rural Housing
12 works
₹3.24 L sanctioned
₹75,000 spent (23%)
09
Community Sanitary Complex
1 works
₹53,000 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)