Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
15
Sanctioned (pure scheme)
₹61.43 L
Expenditure since inception
₹14.90 L
Balance cost (unspent)
₹46.53 L
Wage ₹27.74 L · Material ₹18.79 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
4 works
₹38.11 L sanctioned
₹9.15 L spent (24%)
02
Constr of GP Bhawan
1 works
₹10.00 L sanctioned
₹1.55 L spent (16%)
03
Farm Pond
1 works
₹4.51 L sanctioned
₹261 spent (0%)
04
Land Development
2 works
₹3.84 L sanctioned
₹98,136 spent (26%)
05
Underground Dyke for Ground Water Recharge
1 works
₹3.56 L sanctioned
₹2.77 L spent (78%)
06
Rural Housing
6 works
₹1.41 L sanctioned
₹44,343 spent (31%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)