Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 06:53:12.593559
Works ongoing
11
Sanctioned (pure scheme)
₹47.90 L
Expenditure since inception
₹2.08 L
Balance cost (unspent)
₹45.83 L
Wage ₹24.22 L · Material ₹21.61 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹19.99 L sanctioned
₹0 spent (0%)
02
Land Development
1 works
₹14.90 L sanctioned
₹0 spent (0%)
03
Plantation
3 works
₹7.94 L sanctioned
₹1.72 L spent (22%)
04
Construction of Bund
2 works
₹3.99 L sanctioned
₹35,100 spent (9%)
05
Rural Housing
4 works
₹1.08 L sanctioned
₹0 spent (0%)
06
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)
09
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)