Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
61
Sanctioned (pure scheme)
₹87.70 L
Expenditure since inception
₹55.59 L
Balance cost (unspent)
₹32.10 L
Wage ₹22.04 L · Material ₹10.06 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Cattle Shed
1 works
₹37.85 L sanctioned
₹37.52 L spent (99%)
02
Rural Housing
48 works
₹11.28 L sanctioned
₹7.88 L spent (70%)
03
Grass Land Development
1 works
₹8.99 L sanctioned
₹71,825 spent (8%)
04
Plantation
4 works
₹8.08 L sanctioned
₹3.44 L spent (43%)
05
Construction of Well
3 works
₹7.31 L sanctioned
₹5.67 L spent (78%)
06
Construction of Tank
2 works
₹6.98 L sanctioned
₹17,680 spent (3%)
07
Construction of Trench
1 works
₹5.35 L sanctioned
₹18,270 spent (3%)
08
Well Recharge
1 works
₹1.85 L sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)