Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
42
Sanctioned (pure scheme)
₹1.07 Cr
Expenditure since inception
₹59.51 L
Balance cost (unspent)
₹47.72 L
Wage ₹29.53 L · Material ₹18.19 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
17 works
₹52.90 L sanctioned
₹24.29 L spent (46%)
02
Construction of Well
4 works
₹23.03 L sanctioned
₹13.57 L spent (59%)
03
Construction of Road and Culvert
1 works
₹13.68 L sanctioned
₹12.67 L spent (93%)
04
Construction of Tank
2 works
₹10.02 L sanctioned
₹4.82 L spent (48%)
05
Rural Housing
17 works
₹3.99 L sanctioned
₹2.35 L spent (59%)
06
Farm Pond
1 works
₹3.61 L sanctioned
₹1.81 L spent (50%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)