Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
4,998
Sanctioned (pure scheme)
₹59.75 Cr
Expenditure since inception
₹23.34 Cr
Balance cost (unspent)
₹36.41 Cr
Wage ₹22.89 Cr · Material ₹13.52 Cr
Expenditure trend
₹56.93 Cr
This Week
₹182.70 Cr
Last Week
▼ 68.8% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Mandays trend
2,63,410
This Week
21,46,699
Last Week
▼ 87.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
512 works
₹14.44 Cr sanctioned
₹4.76 Cr spent (33%)
02
Construction of Tank
61 works
₹9.89 Cr sanctioned
₹3.64 Cr spent (37%)
03
Rural Housing
3,860 works
₹9.03 Cr sanctioned
₹4.00 Cr spent (44%)
04
Construction of Well
193 works
₹7.61 Cr sanctioned
₹3.46 Cr spent (46%)
05
Works for Flood Control and Protection
30 works
₹3.08 Cr sanctioned
₹1.54 Cr spent (50%)
06
Construction of Check Dam/Stop Dam
30 works
₹2.12 Cr sanctioned
₹84.25 L spent (40%)
07
Construction of Road and Culvert
14 works
₹2.07 Cr sanctioned
₹1.40 Cr spent (68%)
08
Farm Pond
68 works
₹1.96 Cr sanctioned
₹44.81 L spent (23%)
09
Construction of Bund
45 works
₹1.39 Cr sanctioned
₹59.03 L spent (43%)
10
Land Development
13 works
₹1.36 Cr sanctioned
₹24.75 L spent (18%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 3,860 9.03 4.00 5.03
44%
2 Plantation 512 14.44 4.76 9.68
33%
3 Construction of Well 193 7.61 3.46 4.14
46%
4 Farm Pond 68 1.96 0.45 1.51
23%
5 Construction of Tank 61 9.89 3.64 6.25
37%
6 Well Recharge 46 0.96 0.34 0.62
35%
7 Construction of Bund 45 1.39 0.59 0.80
43%
8 Construction of Check Dam/Stop Dam 30 2.12 0.84 1.27
40%
9 Works for Flood Control and Protection 30 3.08 1.54 1.55
50%
10 Solid and Liquid Waste Management 20 1.14 0.54 0.60
47%
11 Constr of Cement Concrete Roads 15 0.27 0.10 0.17
38%
12 Construction of NADEP/Vermi Compost Pit 14 0.15 0.03 0.12
19%
13 Construction of Road and Culvert 14 2.07 1.40 0.67
68%
14 Land Development 13 1.36 0.25 1.11
18%
15 Construction of Percolation Tank 13 0.32 0.03 0.29
10%
16 Construction of Trench 12 0.74 0.20 0.54
27%
17 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 8 0.28 0.09 0.19
33%
18 Constr of Compound wall 7 0.88 0.21 0.67
24%
19 Community Sanitary Complex 6 0.09 0.02 0.08
16%
20 Constr of GP Bhawan 4 0.50 0.40 0.10
80%
21 Repair & maint of Pond/ Tank 4 0.26 0.05 0.20
21%
22 Repair & maint of Road 3 0.16 0.15 0.01
91%
23 Construction of Spur 2 0.07 0.01 0.06
13%
24 Terracing 2 0.16 0.07 0.09
44%
25 Nursery Development 2 0.04 0.00 0.04
4%
26 Construction of Toilets 2 0.03 0.01 0.02
24%
27 Culvert 2 0.19 0.01 0.18
3%
28 Repair & Maint of Check Dam/Stop Dam 1 0.03 0.00 0.03
8%
29 Boulder Check/Gully Plug 1 0.03 0.00 0.03
10%
30 Cattle Shed 1 0.15 0.05 0.10
36%
31 Constr of Food Grain storage 1 0.08 0.00 0.08
1%
32 Construction of Canal 1 0.06 0.00 0.06
0%
33 Construction of Play field 1 0.02 0.00 0.02
19%
34 Construction of Recharge Pits 1 0.03 0.01 0.03
25%
35 Lining of Canal 1 0.03 0.01 0.02
28%
36 Repair & Maint of Community infrastructure 1 0.07 0.05 0.02
75%
37 Repair & maint of Water Harvesting Structures 1 0.06 0.03 0.03
54%
Total 4,998 59.75 23.34 36.41
All 37 rows (zero-value rows hidden) ⇩ Export to Excel