Monitor — Ongoing Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Works ongoing
38
Sanctioned (pure scheme)
₹58.70 L
Expenditure since inception
₹12.06 L
Balance cost (unspent)
₹46.64 L
Wage ₹22.41 L · Material ₹24.23 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
9 works
₹16.81 L sanctioned
₹6.22 L spent (37%)
02
Terracing
1 works
₹15.91 L sanctioned
₹1.27 L spent (8%)
03
Constr of Cement Concrete Roads
2 works
₹9.98 L sanctioned
₹27,792 spent (3%)
04
Construction of Percolation Tank
4 works
₹6.39 L sanctioned
₹72,393 spent (11%)
05
Rural Housing
11 works
₹2.58 L sanctioned
₹1.90 L spent (73%)
06
Construction of Crematorium
1 works
₹2.45 L sanctioned
₹2,700 spent (1%)
07
Construction of Recharge Pits
7 works
₹1.81 L sanctioned
₹1.10 L spent (60%)
08
Farm Pond
1 works
₹1.39 L sanctioned
₹34,154 spent (25%)
09
Constr of Compound wall
1 works
₹1.12 L sanctioned
₹1,930 spent (2%)
10
Well Recharge
1 works
₹25,899 sanctioned
₹18,523 spent (72%)