Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
53
Sanctioned (pure scheme)
₹1.13 Cr
Expenditure since inception
₹65.21 L
Balance cost (unspent)
₹47.69 L
Wage ₹20.25 L · Material ₹27.45 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
18 works
₹32.90 L sanctioned
₹4.57 L spent (14%)
02
Construction of Road and Culvert
1 works
₹23.33 L sanctioned
₹22.72 L spent (97%)
03
Repair & maint of Pond/ Tank
2 works
₹17.24 L sanctioned
₹15.27 L spent (89%)
04
Well Recharge
2 works
₹11.45 L sanctioned
₹8.45 L spent (74%)
05
Community Sanitary Complex
1 works
₹5.98 L sanctioned
₹57,132 spent (10%)
06
Construction of Percolation Tank
3 works
₹5.96 L sanctioned
₹5.46 L spent (92%)
07
Construction of Well
2 works
₹4.99 L sanctioned
₹3.79 L spent (76%)
08
Rural Housing
20 works
₹4.68 L sanctioned
₹3.22 L spent (69%)
09
Farm Pond
1 works
₹3.33 L sanctioned
₹3,420 spent (1%)
10
Construction of Bund
1 works
₹2.02 L sanctioned
₹17,496 spent (9%)