Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
33
Sanctioned (pure scheme)
₹69.37 L
Expenditure since inception
₹28.29 L
Balance cost (unspent)
₹41.08 L
Wage ₹20.25 L · Material ₹20.83 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
8 works
₹20.54 L sanctioned
₹9.68 L spent (47%)
02
Construction of Check Dam/Stop Dam
1 works
₹14.55 L sanctioned
₹4.57 L spent (31%)
03
Construction of Percolation Tank
2 works
₹9.79 L sanctioned
₹8.07 L spent (82%)
04
Goat Shelter
1 works
₹7.92 L sanctioned
₹2.73 L spent (34%)
05
Plantation
2 works
₹7.89 L sanctioned
₹25,872 spent (3%)
06
Well Recharge
1 works
₹4.45 L sanctioned
₹31,656 spent (7%)
07
Rural Housing
18 works
₹4.23 L sanctioned
₹2.67 L spent (63%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)