Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
40
Sanctioned (pure scheme)
₹49.65 L
Expenditure since inception
₹19.10 L
Balance cost (unspent)
₹30.55 L
Wage ₹17.23 L · Material ₹13.32 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
6 works
₹18.15 L sanctioned
₹4.41 L spent (24%)
02
Construction of Percolation Tank
2 works
₹9.80 L sanctioned
₹4.31 L spent (44%)
03
Rural Housing
17 works
₹4.59 L sanctioned
₹3.13 L spent (68%)
04
Plantation
2 works
₹3.75 L sanctioned
₹1.78 L spent (47%)
05
Land Development
2 works
₹3.53 L sanctioned
₹1.59 L spent (45%)
06
Farm Pond
2 works
₹2.95 L sanctioned
₹1.35 L spent (46%)
07
Boulder Check/Gully Plug
1 works
₹1.93 L sanctioned
₹51,696 spent (27%)
08
Construction of Bund
1 works
₹1.71 L sanctioned
₹35,826 spent (21%)
09
Construction of Check Dam/Stop Dam
1 works
₹1.65 L sanctioned
₹65,722 spent (40%)
10
Well Recharge
4 works
₹1.04 L sanctioned
₹54,156 spent (52%)