Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
52
Sanctioned (pure scheme)
₹1.16 Cr
Expenditure since inception
₹60.52 L
Balance cost (unspent)
₹55.08 L
Wage ₹32.69 L · Material ₹22.39 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
6 works
₹71.04 L sanctioned
₹30.43 L spent (43%)
02
Construction of Road and Culvert
1 works
₹14.71 L sanctioned
₹14.61 L spent (99%)
03
Rural Housing
34 works
₹7.99 L sanctioned
₹6.91 L spent (86%)
04
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.97 L spent (99%)
05
Plantation
2 works
₹4.66 L sanctioned
₹1.26 L spent (27%)
06
Construction of Well
1 works
₹4.65 L sanctioned
₹85,031 spent (18%)
07
Farm Pond
3 works
₹2.59 L sanctioned
₹3,915 spent (2%)
08
Well Recharge
1 works
₹2.53 L sanctioned
₹12,738 spent (5%)
09
Construction of Bund
2 works
₹1.60 L sanctioned
₹57,449 spent (36%)
10
Constr of Gabion
1 works
₹83,368 sanctioned
₹76,082 spent (91%)