Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
15
Sanctioned (pure scheme)
₹1.03 Cr
Expenditure since inception
₹27.80 L
Balance cost (unspent)
₹75.34 L
Wage ₹37.53 L · Material ₹37.80 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
7 works
₹61.13 L sanctioned
₹15.52 L spent (25%)
02
Construction of Road and Culvert
1 works
₹21.55 L sanctioned
₹6.36 L spent (30%)
03
Construction of Well
2 works
₹14.29 L sanctioned
₹5.37 L spent (38%)
04
Construction of Check Dam/Stop Dam
3 works
₹3.37 L sanctioned
₹29,574 spent (9%)
05
Well Recharge
1 works
₹2.52 L sanctioned
₹21,567 spent (9%)
06
Rural Housing
1 works
₹27,000 sanctioned
₹3,654 spent (14%)
07
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
08
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
09
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)