Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
16
Sanctioned (pure scheme)
₹31.00 L
Expenditure since inception
₹15.33 L
Balance cost (unspent)
₹15.68 L
Wage ₹10.68 L · Material ₹5.00 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
2 works
₹13.00 L sanctioned
₹9.65 L spent (74%)
02
Farm Pond
4 works
₹7.07 L sanctioned
₹1.20 L spent (17%)
03
Construction of Percolation Tank
1 works
₹5.54 L sanctioned
₹1.84 L spent (33%)
04
Construction of Bund
1 works
₹3.33 L sanctioned
₹1.42 L spent (43%)
05
Well Recharge
4 works
₹1.08 L sanctioned
₹86,529 spent (80%)
06
Constr of Compound wall
2 works
₹51,229 sanctioned
₹2,316 spent (5%)
07
Rural Housing
2 works
₹46,980 sanctioned
₹32,922 spent (70%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)