Monitor — Ongoing Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Works ongoing
13
Sanctioned (pure scheme)
₹45.52 L
Expenditure since inception
₹24.63 L
Balance cost (unspent)
₹20.89 L
Wage ₹15.13 L · Material ₹5.77 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹16.73 L sanctioned
₹10.97 L spent (66%)
02
Construction of Bund
2 works
₹13.82 L sanctioned
₹7.94 L spent (57%)
03
Plantation
4 works
₹8.91 L sanctioned
₹4.42 L spent (50%)
04
Farm Pond
2 works
₹4.48 L sanctioned
₹74,103 spent (17%)
05
Construction of Check Dam/Stop Dam
1 works
₹1.00 L sanctioned
₹21,663 spent (22%)
06
Rural Housing
1 works
₹23,490 sanctioned
₹18,711 spent (80%)
07
Construction of NADEP/Vermi Compost Pit
1 works
₹20,267 sanctioned
₹1,157 spent (6%)
08
Constr of Cement Concrete Roads
1 works
₹14,000 sanctioned
₹13,999 spent (100%)
09
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)