Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 06:53:12.593559
Works ongoing
19
Sanctioned (pure scheme)
₹38.97 L
Expenditure since inception
₹9,300
Balance cost (unspent)
₹38.88 L
Wage ₹27.49 L · Material ₹11.39 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹14.74 L sanctioned
₹0 spent (0%)
02
Plantation
3 works
₹12.90 L sanctioned
₹0 spent (0%)
03
Construction of Tank
1 works
₹7.55 L sanctioned
₹0 spent (0%)
04
Rural Housing
14 works
₹3.78 L sanctioned
₹9,300 spent (2%)
05
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
06
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)