Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
5
Sanctioned (pure scheme)
₹32.84 L
Expenditure since inception
₹12.16 L
Balance cost (unspent)
₹20.68 L
Wage ₹14.63 L · Material ₹6.04 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
1 works
₹14.06 L sanctioned
₹1.08 L spent (8%)
02
Constr of Cement Concrete Roads
1 works
₹10.54 L sanctioned
₹9.22 L spent (87%)
03
Plantation
2 works
₹5.56 L sanctioned
₹38,106 spent (7%)
04
Construction of Well
1 works
₹2.68 L sanctioned
₹1.49 L spent (56%)
05
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
06
Rural Housing
0 works
₹0 sanctioned
₹0 spent (0%)
07
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)