Rollup last refreshed: 2026-10-15 06:57:05.982177
Works ongoing
13
Sanctioned (pure scheme)
₹22.32 L
Expenditure since inception
₹10.52 L
Balance cost (unspent)
₹11.79 L
Wage ₹4.24 L · Material ₹7.55 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
4 works
₹11.79 L sanctioned
₹7.98 L spent (68%)
02
Solid and Liquid Waste Management
1 works
₹5.89 L sanctioned
₹34,308 spent (6%)
03
Construction of Check Dam/Stop Dam
2 works
₹2.02 L sanctioned
₹59,976 spent (30%)
04
Rural Housing
5 works
₹1.35 L sanctioned
₹65,487 spent (49%)
05
Constr of Cement Concrete Roads
1 works
₹1.27 L sanctioned
₹95,004 spent (75%)
06
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)