Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
20
Sanctioned (pure scheme)
₹21.94 L
Expenditure since inception
₹12.03 L
Balance cost (unspent)
₹9.91 L
Wage ₹5.56 L · Material ₹4.35 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
5 works
₹13.12 L sanctioned
₹6.14 L spent (47%)
02
Construction of Crematorium
1 works
₹2.38 L sanctioned
₹2.00 L spent (84%)
03
Rural Housing
9 works
₹2.03 L sanctioned
₹1.62 L spent (80%)
04
Farm Pond
1 works
₹2.00 L sanctioned
₹58,871 spent (29%)
05
Constr of Cement Concrete Roads
2 works
₹1.32 L sanctioned
₹1.30 L spent (99%)
06
Construction of Bund
1 works
₹73,000 sanctioned
₹4,632 spent (6%)
07
Community Sanitary Complex
1 works
₹37,000 sanctioned
₹33,718 spent (91%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)